Revimac engineers remotely reconditioned and installed IS machine parts during a recent installation at Thailand’s Siam Glass.
The remote installation took place due to the challenges of travel caused by the Covid-19 pandemic.
The installation took place after a fire in December 2019 at Siam Glass's Samutprakarn production plant on Line 3.7. where many parts of an IS machine were completely burnt (pictured below).
Revimac and Siam Glass agreed on the list of parts to be substituted and on the fact to recondition directly on site the machine.
While it was eventually impossible to perform an on-site service, thanks to the cooperation and the good experience and knowledge of Siam Glass Team, with a perfect schedule of activities, a remote service was successfully performed to the satisfaction of both companies.
Revimac Supervisor Engineers were connected with the Siam Glass Team during all the working period by means of pictures, videos, drawings and technical meetings, supervising all the mechanical and electrical installation.
Most of the parts substituted were in the section boxes, as valve blocks, connection piping, electrical part on board.
At the end, the satisfaction to see the machine completely reconditioned and perfectly working was the best result for everybody.