Zippe has installed a batch plant with a batch and cullet conveying system on the new furnace at Indonesian tableware glass producer, PT Culletprima Setia.

The project was realized at the peak of the Corona pandemic. Nevertheless, together with the customer, all challenges were solved in a flexible and collaborative partnership leading to project success.

The new plant was built next to the existing production and feeds the new furnace for tableware with a capacity of 130 t/day and a cullet ratio of 30%.

In addition to the batch plant, Zippe also supplied a scraping conveyor as well as a crusher for the cullet plant.

Commissioning was completed recently, and the plant has operated flawlessly since.